G Richard J. Benjamin Soccer Complex - Field Progress
Richard J. Benjamin Soccer Complex - field progress





Land at start of the project
Land at the start of the project (prior to clearing). Small trees and brush are visible, as is the general downward slope from left to right in the photo -10/14/00

Early October 2000

Newly acquired fields (behind existing Oswego Middle School fields)
after preliminary brush hogging (October 28, 2000)




another late October 2000 view
Another October 28, 2000 view of the new fields (further north)


October 2000 north-south view
A north-south October 28 view of the new fields after brush hogging and removal of small trees. Notice the furrows left behind from earlier use of the fields as a cow pasture.

ductile iron water pipes
8/28/01 - 1000' of ductile iron water pipes stored on corner of property. Tug Hill Construction, Inc. begins work.



Water/sewer pipe installation begins
8/30/01 - Vickery Construction begins installing water and sewer lines in the right-of-way bordering Richard Benjamin Blvd.


right of way
9/7/01 - Right-of-way area backfilled, cleaned, and hydroseeded.



9/17/01 - image 1
September 17, 2001 - cuts and fills underway. Notice the tall pile of stripped topsoil awaiting sifting on the left side of this image.

9/17/01 - image 2
View from entrance 9/17/01 - Note that the fabric barrier and base 5" of bank-run gravel that have been added to the west half of the parking lot (visible on the right side of the photo)


9/17/01 parking lot
9/17/01 - gravel and fabric barrier installed on top of graded and rolled surface. Photo taken at midpoint of parking lot.

9/17/01 - soil sifting - near parking lot
9/17/01 - soil sifting - near parking lot

rough grading in progress w/elevation marks
Rough grading in progress - 9/17/01. The ribbons on the posts indicate target elevations.

9/17/01
9/17/01 - Cuts & fills in progress.


backfilled and seeded water & sewer lines
9/17/01 - Backfilled, cleaned, and seeded area along right of way from Mark Fitzgibbons Drive to field complex for water and sewer lines.



completion of rough grading - concession stand area
9/22/01 - Completion of rough grading - concession stand area. The area enclosed by yellow ribbons encloses the grinder-pump station and water line termination near east end of concession/rest room/storage building. This lower tier of the soccer complex also includes 3 small fields (on the west end).

9/22/01 - rough grading lowest tier
View of nearly complete rough grading of lowest tier - 9/22/01. The right portion of the photo provides a view of the parking lot after placement of 5 inches of bank run gravel over a fabric barrier.


rough grading - tier 2 - 9/22/01
9/22/01 - Rough grading near completion on 2nd tier containing two full-size fields (the equipment is located between the two fields).


rough grading - tiers 2 and 3
9/22/01 - Rough grading nearly complete (after rolling) on tier 2 (view from north end facing south). rough grading beginning on tier 3 (1 large field and one small field)


top soil placed  on large fields - tier 1 - final grading in process
9/26/01 - Final grading on Tier 1 and 2 well underway after replacement of 6 or more inches of sifted topsoil. Fields shed water nicely after first heavy rains. Drainage not yet in place.


storm drain tie-in
Precast catch basin installed and backfilled on 10/1/01. The picture above shows the backfilled connection to the Oswego Middle School storm sewer system. 24" pipe was used to connect the two catchbasins. All under field drainage ties into this catchbasin.


new catchbasin
10/1/01 - newly installed catchbasin w/ view of 24" pipe



Cover placed on catchbasin
10/2/01- cover placed on catchbasin


completion of 5" bank-run gravel base for parking lot
10/2/01 - Completion of 5" bank-run gravel base for parking lot area for entire surface except for the area by entrance in which drainage pipes will be installed.

final grading underway for tier 4
10/4/01 - Final grading underway for tier 4 (containing 1 midsize field). This picture provides a view of nearly the entire length of the field complex (facing north). The relatively small size of the equipment and cars in the parking lot provides a sense of scale.


drainage installation begins
10/8/01 - installation of 6" drainage tile begins along the periphery of fields.


4" and 6" drainage tiles installed under 2 of the large fields.
10/8/01 - 4" drainage tiles installed under one of the large fields. Perhiperal lines are 6" perforated pipe. All pipes are set in #1 pea gravel. Isbel & Sons provided the drainage installation. The gravel was provided by Lazarek Sand & Gravel.


close up of machine that laid drainage tile
10/8/01 - A closeup of the machine that trenched, laid pipe, and backfilled trench with gravel.


installation of 3" of crusher-run gravel in far side of parking lot
10/10/01 - installation of top layer (3") of crusher-run gravel on far end of parking lot.


clean up after drainage installation
10/10/01 - cleanup begins after installation of drainage tiles. Tug Hill Construction removed large rocks by hand (with the assistance of a golf cart). The fields were then Harley raked, final graded, and rolled.


parking lot nearing completion
10/12/01 - The parking lot area is extended toward the entrance now that drainage lines have been installed.


preparation for seeding
10/12/01 - Fields are raked immediately prior to seeding. (Notice the cleanup after the drainage installation.)


seeding in progress
10/12/01 - Brillion seeding in process. Fields were double-seeded (both horizontally and vertically)


small drains installed
10/12/01 - Nine 12" drains were installed in corners of large fields and other low spots and connected to the 6" drainage lines.


parking lot nearing completion
10/12/01 - Fabric barrier and crusher-run gravel is extended toward field entrance.


Brillion seeding
10/12/01 - Closeup of brillion seeding in progress.


jute mesh installation
10/12/01 - Jute mesh installation begins along slopes.





seeding completed - jute mesh installed
10/13/01 - Fields have been completely seeded. Jute mesh has been installed along slopes bordering middle school fields (on left) and on all slopes between tiers (two such slopes are visible in the distance).





roof trusses
10/04 - Installation of roof trusses begins. Trusses are lifted by Todd Dudley (who donated the use of his truck and time). Volunteers working on the installation of the trusses included Todd Dudley (and family), Sam Tripp, Mike Amedio, Pat O'Neill, J. Jaskula, Tim Kraft, Bob Morgan, Jamie Cullinan, Andy Michaud, Jim Reynolds (in red jacket in foreground), Lou Angelina (on left side in the foreground), John R. Kane, and John C. Kane.


roof trusses
10/04 - Another view of the start of the work on the trusses.